Present Stage of the Project
The
stern section of the decking has been removed to enable replacement of
rotted sections of the ribs and deck support beams. The temporary plastic
cover sheet is to reduce the effects of sun and rain on the existing structures.
A temporary gantry (crane) has been installed within the stern section
of the vessel.
The base of the gantry is braced on a solid section
of the keel and wire stays on each side are tied back to solid fixing
points amidships.
The May Queen has been leveled, using the water surface
as a reference point, and the stern section has been lifted to take the
droop and slight twist out of the shape of the hull above the waterline.
The
lifting has been accomplished using turnbuckles attached to the gantry
system. Replacement of internal ribs and bracing will now be undertaken
to maintain the restored shape of the vessel.
Update November 2002
...
|