Further Stage of the Project (with
approx 12 months to go)
 Recent
work on the vessel has seen the installation of new wooden frames throughout
the hull. This has been undertaken wherever possible, alongside the original
timbers to retain the appearance and the atmosphere of the early workmanship.
The new frames were fitted whilst the May Queen was
afloat, however fastening of the outside planking to the frames and the
recaulking of the seams had to be done when she was up on the slip in
August 2002.
The
vessel is now considerably stronger below the waterline than she has been
for some considerable time and seepage of seawater through the planking
has been virtually eliminated.
The next stages will see:
- the fitting of a new steel breasthook, to strengthen
the stem, with the original wooden item replaced as a cover (refer to
the photo);
- replacement of staunchions to hold the original
Huon Pine deck rail;
- fitting of some replacement upper planking
- fitting of deck beams and new Celery Top Pine decking.
The
May Queen preservation and maintenance project has received international
recognition by the World Ship Trust with the granting of the Trusts Maritime
Heritage Award.
This award is presented to a select number of
project groups worldwide involved with the preservation and/or restoration
of maritime heritage vessels.
Update August 2001
...
|